Metrostav logo
Menu
Centrála společnostiKoželužská 2450/4, Praha 8

Reconstruction of the Old Town Weir, River Vltava km 53.18

Other Civil Engineering Works
Prague

The aim of the construction project was to secure the damaged structures of the listed fixed weir by Charles Bridge to withstand the increased flows of the River Vltava and to restore its historical appearance from the 13th century. 

Basic information

Project Investor:

Povodí Vltavy, s.p.

Project Designer:

VH-TRES spol. s.r.o.

Project Duration:

04/2021 – 07/2023

Reconstruction of the Old Town Weir, River Vltava km 53.18
Obrázek

Characteristics

The builders demolished the original weir spillway and built a new one made of oak beams and granite filling. They installed a new weir crown and a breakaway edge made of granite stones, and created a stone area at the bottom of the weir. The work also included the installation of permanently fitted footings for temporary barriers on the concrete front of the weir, including the supply of mobile parts.

Project in numbers

  • 320 m
    Approximate length of the inclined weir
  • 2,100 m
    Total length of oak beams used
  • 1,155 m2
    Area fitted with granite slabs

Uniqueness of construction project

The builders used original technology as much as possible. They had the oak harvested in winter made into rafts, which were then soaked in water for over a month. After being towed to the construction site, the beams remained submerged until assembly and were sprinkled with water afterwards until reflooding. During construction, workers used floating excavators and cranes, as well as pusher boats to bring and remove materials. The reconstruction finished nine months ahead of schedule and won one of the top prizes at the Water Management Construction Project of the Year 2023 awards.

Obrázek
Obrázek
Obrázek
Obrázek

© 2021 Metrostav - Jakýkoliv obsah této stránky není možné šířit bez souhlasu společnosti Metrostav a.s. | Metrostav a.s. je řídicí společností koncernu Skupina Metrostav